Login to Portal

Forgot your password? Click here.

Don’t have an account? Click here.

IUOE

CT Construction Digest Thursday September 2, 2021

Deadline passes, Connecticut Port Authority remains confident in State Pier project



Greg Smith 

New London — The Connecticut Port Authority has failed to meet an Aug. 31 deadline to obtain a federal permit for work on the $235.5 million State Pier construction project but appears confident its offshore wind partners will not decide to pull funding.

The Aug. 31 deadline is contained in an amendment added earlier this year to a Harbor Development Agreement between the port authority, state and joint venture partners Ørsted and Eversource.

The amendment allowed for the release of more than $50 million from Ørsted/ Eversource to enable the port authority to continue to approve contracts associated with the ongoing permitted work at State Pier. The partners have committed $70 million toward the project.

The new terms allow Ørsted and Eversource the opportunity to pull a significant portion of that promised funding, which in turn would force the CPA to rethink the scale of the project. There has been no indication either side is thinking about a scaled-back project.

Ørsted and Eversource, in a statement, said they plan to meet with representatives from the state and CPA to discuss plans moving forward.

“We expect that the final Army Corps permit will be issued soon and we will come together with the State to assess schedule impact — if any,” the statement reads.

The amendment to the Harbor Development Agreement states that if an Aug. 31 deadline is not met, the two sides are to meet “and use diligent commercial efforts to either revise the applicable deadline(s)” or “revise this Harbor Development Agreement and the Sublease Agreement no later than September 15, 2021 to reflect an alternate construction schedule, cost estimates and or funding plan. ...”

The deadline referenced in the agreement included a state permit and release of state funding for the project, two conditions that have been met.

A spokesperson for the Army Corps of Engineers said this week a decision for a federal permit is not expected until the end of the month. The permit would allow for filling in 7.2 acres between the two existing piers, which is a crucial part of the project.

CPA Board Chairman David Kooris explained to the CPA board in June that it is a “worst case scenario” that the two sides do not agree to an extension of the deadline, but if it happens, Ørsted/Eversource is entitled to withdraw a portion of its funding. There are limitations on how much Ørsted/Eversource could pull out and would exclude the $22.5 million previously committed by Deepwater Wind — an offshore wind company purchased by Ørsted — and $2.5 million in operating funds, as well as any funding that already has been expended on the project.

Kooris has said the deadline was a way for Ørsted/Eversource to mitigate its risk of having released its funding for a project.

A meeting between the two sides is expected to occur before Sept. 15. Andrew Lavigne, the CPA’s manager of business development and special projects, said Wednesday that “we all remain committed to developing a plan to deliver the project in its full scope within a mutually agreeable budget and time frame.”

“Ultimately we and our partners want to build to full scope. That is the core of the discussions to be had between now and September 15,” he said in an email.

Meanwhile, work continues at State Pier, and a large cargo ship, BBC Eagle, this week was offloading steel pipes for use in reconstructing the northeast bulkhead and heavy-lift pad, work that is not dependent on the federal permit.


Congress is poised to make a major investment in rail. Is it enough for CT?

MARK PAZNIOKAS

At a time of hype and headlines about trillions the president wants to invest in infrastructure, a railroad man with a long memory oversees the Department of Transportation in Connecticut, a state that’s been an unreliable steward of rail since the neglected New Haven Line was left to its care half a century ago.

Joseph J. Giulietti, recruited as DOT commissioner immediately after Gov. Ned Lamont’s election in 2018, started on the New Haven Line in 1971 as a 19-year-old conductor for Penn Central, then a dying railroad about to cede ownership of the line to a state unready for the responsibility.

He was there when Penn Central gasped its last and yielded management of commuter rail to Conrail in 1976, and when Metro-North was born as a subsidiary of New York’s Metropolitan Transportation Authority and took over in 1983. Giulietti left in 1998 for a rail job in Florida, returning in 2014 as Metro-North’s president.

Giulietti is 69 now, and the DOT is the last stop in a 50-year career that neatly coincides with passenger rail’s transition to a wholly governmental responsibility. The buzz in Washington is that Congress is poised to make its biggest investment in rail since it created Amtrak from the ruins of 20 private railroads in 1971.

Joe Biden became a regular Amtrak passenger two years later, a senator who would commute from Delaware to Washington for 36 years. The new House Appropriations chair is Rosa L. DeLauro of New Haven, an Amtrak regular since taking office 30 years ago. And Amtrak Joe is in the White House now.

“If there was ever a time that the stars are starting to align, we’re seeing it,” Giulietti said.

Behind the headlines are hard realities. The political coalition behind the infrastructure bill is fragile, and the $66 billion it offers for rail over five years is both historic and inadequate. A little more than half would go to the northeast corridor between Boston and Washington, the one region where Amtrak runs trains at a profit.

The Northeast Corridor Commission, whose members represent Amtrak, the U.S. Department of Transportation and the eight states and nine transit agencies on the corridor, recently released Connect NEC 2035, its vision for speeding rail. Dubbed C35, it is a $117 billion, 15-year plan.

Giulietti says he needs at least $8 billion for the portion in Connecticut, much of it for long-overdue work on the New Haven Line. His priorities, outlined in Time for CT, a plan released in June, align with C35’s priorities, not surprising given that Giulietti is a voting member of the commission. C35, which breaks up the corridor into regions, calls for $9 billion for work on the section in Connecticut and Westchester County, N.Y.

“The problem is we have so badly underinvested in the northeast rail corridor that there is $40 billion, at least, of what we call state-of-good-repair projects that we just need to do in order to make sure that the rail doesn’t fall apart, projects we need to do just to maintain existing service,” said U.S. Sen. Chris Murphy, D-Conn. “And so, the bipartisan proposal doesn’t even fund the state-of-good-repair projects. Now, that’s devastating for us in Connecticut.”

Tectonic changes

The story of the New Haven Line is the story of passenger rail.

It reflects tectonic changes in postwar American life and commerce, including the shift from rail to highways for the movement of freight and passengers. And it exposes a shared failing of capitalists and politicians — the tendency to sacrifice the future for immediate gains, on balance sheets or at the polls.

Metro-North is a case in point.

After building a reputation for good service, it began in 2013 to experience a string of accidents attributed to a mix of factors, including insufficient maintenance and a culture that came to value on-time performance over safety. Giulietti, who then was the executive director of the Tri-Rail system in South Florida, was asked to come back and trouble-shoot a railroad under a microscope from the Federal Rail Administration and the National Transportation Safety Board.

“Nobody wanted to touch Metro-North, nobody who had a career ahead of them,” Giulietti said. “Because the FRA had 75 officers on the property, and there were five NTSB investigations going on.”

Giulietti stayed three years, winning good reviews for changing the culture of the railroad by resisting demands for quick improvements to service in favor of a longer-term push for first re-establishing safety and reliability. He retired in 2017.

Giulietti was a semi-retired consultant when Lamont’s transition team targeted him as a priority hire. His predecessor, James P. Redeker, also had a background in transit, but Lamont wanted a fresh start.

“I love the guy because he was the president of Metro-North,” Lamont said. “We didn’t have a great relationship with New York. And I just figured two and a half years ago, if I’m going to speed up rail from New Haven to New York, who better to take the lead on that than the guy who used to run Metro-North? He’s a great rail guy. He’s surrounded with really good guys.”

Paul Mounds, the governor’s chief of staff, said the attraction to Giulietti was twofold: Giulietti had a reputation for fixing things and telling bosses and customers unpleasant truths; and his resume gave the new administration a certain gravitas on transportation.

A career rail guy

Giulietti was a student at Southern Connecticut State University in New Haven, his hometown, when he went to work on the railroad.

The college gig turned into a career pushing trains as a locomotive engineer, then rising through the ranks, mastering the arcane skills of scheduling trains, appreciating the limits imposed by track geometry, learning a little politics and recognizing why a simple mud puddle can foretell trouble.

Career rail guys inevitably are rail historians, students of disappointment and decay. To Giulietti, there is no mystery why the trip from New Haven to Grand Central Terminal takes longer today than in 1970, when Penn Central filed for bankruptcy protection. It is the consequence of disinvestment.

“That was very deliberate,” Giulietti said. “Penn Central sucked out every dollar.”

His assessment of Connecticut’s stewardship of its rail lines is less quotable but nonetheless damning.

Connecticut has been slow to put those dollars back, moving at glacial speeds to modernize signalization, among other things. (Don’t get him going about mud spots.) The culture and DNA of the DOT is dominated by men and women who design, build and maintain highways and roads, not public transit. And, unlike most other states, no significant transportation improvements come without borrowing.

“I always felt bad for the people that were in the position I’m in right now, because they didn’t have the support to get the money to go into the maintenance that was necessary,” Giulietti said.

Connecticut owns trains capable of reaching 100 mph, and the maximum authorized speed limit where the New Haven Line is in good repair is 90 mph. But the average authorized speed is 66 mph — with some spots restricted to 37 mph and, at least one, just 30 mph. In other words, for many commuters, it’s faster to drive.

“When I came back as the president of Metro-North, I couldn’t believe how many speed restrictions existed on this rail system,” Giulietti said.

His Time for CT plan drew a scathing review from one prominent transportation writer, Alon Levy. Like C35, the improvements in the Time for CT, a plan would shorten the ride between New Haven and Grand Central by 25 minutes over the next 15 years. With new express service, some trips could be 10 minutes quicker next year.

Levy called it “shelf art,” a plan whose costs are “high enough and the benefits low enough that it’s unlikely the report will lead to any actionable improvement.” More than anything, Levy wrote, the needs outlined amount to indictment of DOT’s poor maintenance practices.

Giulietti doesn’t dispute the indictment of the DOT’s maintenance history. But he is adamant that Time for CT, and the needs assessment on which it is based, are grounded in reality.

“There’s no bullshit in that report,” Giulietti said. “It’s very, very factual, detailed and laid out.”

The B.S. reference may reflect sensitivity to criticism that the DOT and Northeast Corridor Commission set their sights too low. A non-governmental organization, North Atlantic Rail, seemed to emerge from nowhere after the New Year to goad transit planners to be more ambitious.

North Atlantic floated a $105 billion concept for 200-mph bullet trains from Boston to New York, high-speed service between Hartford and Providence and Springfield and Boston, and a tunnel under Long Island Sound. There is no rail right-of-way between Hartford and Providence, and the only rail between Springfield and Boston are owned by freight lines, not Amtrak.

Unlike the Northeast Corridor Commission, no one connected to North Atlantic owns or operates rail.

North Atlantic succeeded in getting language into a House infrastructure bill that could be useful in establishing it as a multi-state compact, but it was scaled back from a version that U.S. Rep. Joe Courtney, D-2nd District, said would have given it a federal charter with powers to override state transportation agencies.

“Believe it or not, it actually would explicitly exclude the participation of state departments of transportation, just completely override all the existing checks and balances,” Courtney said. The offending language was stripped, but the attempt was jarring.

Hartford Mayor Luke Bronin is North Atlantic’s biggest backer in Connecticut, and he notes that its early priorities closely align with C35. But he is unapologetic about the scope of the group’s ambition, even if aspects prompt eye rolls.

“Of course, during the Trump era, ‘Infrastructure Week’ became a joke, but after Biden’s election, it became clear that we might have a historic, once-in-a-generation opportunity to make transformative infrastructure investments,” Bronin said.

U.S. Sen. Richard Blumenthal, D-Conn., said the delegation speaks with one voice about rail money: Giulietti’s priority list is their list.

Murphy was blunter.

“Listen, we’re not going to build a tunnel under Long Island Sound. I mean, I wish we could think that big, but I do not think that that’s worth our time and energy,” Murphy said. “It’s not feasible to build a tunnel under Long Island Sound or build a whole new rail line through eastern Connecticut.”

Murphy called North Atlantic a distraction that the northeast cannot afford, an assessment Giulietti and senior staff find reassuring.

The importance of getting Amtrak and the eight states on the corridor to speak, more or less, with one voice to Congress cannot be understated in Giulietti’s view. The point was underscored when he interrupted an interview to take a call from a counterpart in New Jersey, then ended it to keep an appointment with Connecticut’s senior senator, Blumenthal.

Lamont’s goal for the system when he took office was 30-30-30 — 30 minutes from Hartford to New Haven, 30 from New Haven to Stamford, and 30 from Stamford to Grand Central. 

After 15 years of improvements, Time for CT would take 25 minutes off a New Haven-to-Grand Central ride that now takes nearly two hours on average. With new express service, some trips could be 10 minutes quicker next summer.

The mud spots

There is no backlog of shovel-ready projects, should the federal spigot start flowing, nor is the state necessarily ready to contribute whatever matching funds are required.

The first project in Time for CT would improve drainage and lessen curves, allowing higher speeds in the Bridgeport to Stratford area. Drainage is not as sexy as new cars, stations or bridges, but mud spots are the bane of railroads.

Mud spots are a misnomer, a railroad’s bland name for something dangerous. The recipe for temporarily transforming solid ground into an unstable slurry is simple: Add water, then vigorously vibrate — say, by running a heavy train over it 50 times a day. 

The New Haven Line has 95 mud spots and 5,700 compromised concrete ties.

“That first project is $250 million,” said Richard W. Andreski, the chief of the state Bureau of Public Transportation. “We have the funding to do the preliminary design. We don’t have funding for the final design and construction.” 

So, Connecticut waits for news from Washington. 

Giulietti knows that the governor, who spent his first year on a failed effort to return highway tolls to Connecticut, is eager to see improvement.

“He’s always frustrated, because he wants it to go faster, and he wants it to go faster tomorrow, all right?” Giulietti said.

Giulietti has his own frustrations. It takes him a year to hire an engineer under Connecticut’s sclerotic hiring rules and the fondness of the Office of Policy and Management to keep jobs open and save money.

Connecticut’s reliance on plain-vanilla financing — going to the bond market — limits what it can borrow. Wall Street demands a 2-1 ratio of revenue to debt service costs, a protection for bond buyers.

Nothing about rail is simple.

Any major improvements require coordination in design, financing and construction. In Connecticut, the New Haven Line is owned by the state and used by Metro-North and Amtrak. CTrail, which is part of DOT, offers passenger rail on tracks owned by Amtrak between New Haven and Springfield on the Hartford Line and between New London and New Haven on Shoreline East.

Who pays for it all

Using a formula set by federal law, Connecticut pays Amtrak for a share of the upkeep on the tracks used by CTrail, and Amtrak pays Connecticut for the use of the New Haven Line. When the accounting is done, the net is $4 million paid to Connecticut.

Europe and Japan have built and maintained modern rail systems, helped by consistent funding that eludes rail and other infrastructure in Connecticut and much of the U.S.

The state raised the wholesale fuel tax in 2005, but less than half the $1.84 billion revenues raised from that tax would be used for transportation through 2011, when Gov. Dannel P. Malloy took office and confronted a deficit equal to nearly 20% of general fund spending. He eventually increased capital funding for transportation, and Lamont took office in 2019 promising to build on that progress.

Lamont failed to win approval of highway tolls to stabilize the state’s shaky Special Transportation Fund, which uses fuel taxes and share of sales taxes to pay DOT’s budget and debt service on transportation projects. An initial plan would have raised $740 million annually; a downsized revision, $320 million. He settled this year for a stopgap, a $90 million highway user fee on large trucks.

“I’m always amused that the Republicans in Washington claim they want to pay for the infrastructure bill with a user fee, and the Republicans in Connecticut said, ‘Over my dead body.’ Essentially, the president and I have the same issue,” Lamont said. “Everybody supports infrastructure. Nobody really wants to pay for it.”

In Connecticut, the state may own parking lots around Metro-North stations, but they often are controlled by the municipality through leases.

“It’s unlike the rest of the country, where you have that cooperation and multiple forms of revenue supporting a system,” said Garrett Eucalitto, the deputy commissioner since January 2020. “So, that’s one way we’re not set up for success.”

His expertise is transit-oriented development and infrastructure finance, and he was brought to the DOT to make changes.

“We’ve posted for a job or two that are going to bring in a different type of financing mindset,” Eucalitto said. “We’re looking for a firm to come in and help us develop new policies and procedures, to evaluate projects for alternative financing and delivery, as well, to build that in-house expertise.”

Giulietti said the governor and legislators would like to see the projects outlined in Time for CT finished long before 2035.

“Can we go faster than what’s in that plan?” Giulietti said. “If we had the money, we can do a hell of a lot faster.”

He knows where to find the mud spots.


East Haddam Swing Bridge will get $58M overhaul. Here's what is planned.

Cassandra Day

EAST HADDAM — The state will launch a two-year, $58.2 million project next spring to overhaul the 108-year-old East Haddam Swing Bridge, which carries Route 82 over the Connecticut River, connecting the town center to neighboring Haddam.

Construction is estimated to take approximately two-and-a-half years — from spring 2022 through fall 2024.

The structure, dedicated in 1913, totals about 885 feet in length, Supervising Engineer Derick Lessard said during last week’s Middlesex County Chamber of Commerce Haddam & East Haddam Division meeting. At the time it was built, the bridge was believed to be the largest of its kind.

The state Department of Transportation initiative is intended to improve safety and access, as well as operations for vehicles, pedestrians and bicyclists traveling on Route 82.

“Improvements include a major rehabilitation of the bridge to extend service life, improve roadway rideability for traveling public, and improve swing span operation reliability,” according to the project’s website.

“We will have some hangups,” Chamber President Larry McHugh said at the meeting, calling it a “very, very important” project. “There will be some hangups and problems,” he said, but, “we will work those problems out.”

The project manager said DOT is taking into consideration surrounding businesses that will be impacted by the work. A residential driveway at Little Meadow Road and Route 82 will be used for equipment staging, so the DOT will be building another on the southern part of the homeowner’s property, Lessard said.

Boat traffic presently flows under span three, he said. “There are times during this process when the navigation channel will have to be closed,” he said, at which time, vessels will temporarily cross under span four.

Smaller boats that can fit under the span without the bridge needing to pivot will be allowed to pass at all times, the project manager said.

Part of the work will be conducted during peak boating season, Lessard said, however, “we’re always going to have a means for boats to go through.”

The project calls for floor beam and deck replacements on span one and two, bearing and joint replacements, substructure repairs, a full replacement of the electrical system, and upgrading the mechanical system, which will make the swing operation “more viable,” he said.

Also, a 6-foot sidewalk will be added on the southern side of the bridge.

Lessard anticipates there will be a 20 percent reduction in the swing span “cycle” time once construction is complete.

Advance warning signs will be posted in the surrounding area, including at the intersection of routes 151 and 82, as well as 82 and 54, he said.

At least 14 days’ notice of closures will be given for any construction. Like on the Arrigoni Bridge, there will be alternating one-way traffic 24 hours a day during this period, he said. Work will continue throughout the year, even during the winter. Detour routes will be designated.

The DOT will communicate with Google Maps and Waze so closures are picked up on GPS, Lessard said..

Increasing the Chester-Hadlyme Ferry operation hours to circumvent construction is under review. The proposed plan is to have the vessel in service Monday to Friday from 5 a.m. to 10 p.m., and extending the season to March through December, weather permitting.

Those with questions can email DOTProject40-141@ct.gov, or Lessard at Derick.Lessard@ct.gov. For up-to-date information, follow East Haddam Swing Bridge Project on Facebook, CTDOT_EHaddamBridge on Twitter and go to easthaddamswingbridgeproject.com.


A restaurant and mini-mall are planned for Sandy Hook. They can't be built before I-84 construction is complete.

Rob Ryser

NEWTOWN - A restaurant and mini-mall approved a year ago east of Newtown High School is waiting on the state to undertake major improvements at the Interstate 84 ramp intersections next door before undertaking construction.

“We are waiting to see what kind of a mess it creates,” said Dinah Walsh of plans to build a 14,000-square-foot restaurant and retail center called Walsh Plaza on Route 34 near Toddy Hill Road. “It’s going to impact our property.”

Walsh is referring a 3-acre site she and her husband James own next door to Exit 11’s on- and off-ramps, which are scheduled to undergo major intersection improvements by the state Department of Transportation this fall.

A DOT official familiar with the $25 million project said on Wednesday that the likely start date was early October. The project is expected to be complete in the fall of 2023.

The goal is to reduce congestion on Route 34 and improve sight lines at the Wasserman Way and Toddy Hill Road intersections by realigning lanes.

Plans call for the off-ramp from I-84 at the Exit 11 interchange to be reconfigured with a new turn lane. In addition, the I-84 eastbound ramp will be “realigned slightly north to accommodate the proposed slip ramp from Route 34.” Route 34 will also be widened to add a westbound bypass-width shoulder for the Newtown High School driveway, the DOT said.

What that means for the approved Walsh Plaza is unclear.

Once DOT construction begins and motorists get used to the new traffic patterns, it’s possible that construction could begin on the mini-mall, Walsh said.

More likely, however, the Walsh Plaza project will have to wait until the ramp reconstructions are nearly complete before clearing ground for its own construction.

“We have to see what the impact is going to be, because they might be using our property to store equipment and materials,” Walsh said.

Walsh said she was not dismayed by the delay.

“A lot of people have reached out about it,” Walsh said. “There’s nothing in that part of town, so we’re excited.”