CT Construction Digest Thursday August 18, 2022
One in Three Projects at State Pier Hit Obstacles, Testing Budget and Timeline
Brendan Crowley
NEW LONDON – Boulders disrupting pile driving for the redevelopment of the New London State Pier could add costs and complicate the schedule of the project, officials said at a Connecticut Port Authority meeting on Tuesday.
Port Authority interim Executive Director Ulysses B. Hammond said that three of nine stages of construction at the State Pier have run into difficulties and run behind schedule in the last month – construction of the south wall of the pier, its toe wall, and the heavy lift platform that will allow for it to be used for offshore wind staging.
Hammond said the contractor Kiewit reported that higher than anticipated rock elevations and obstructions have negatively impacted pile driving progress on the pier, which needs to be substantially completed by March 2023 in order for Eversource and Ørsted to use it for construction of their joint offshore wind project, South Fork Wind.
“I remain optimistic that, under the leadership of our contract administrators, Kiewit, and the entire project team, that the work-around solutions will restore the required productivity rates to enable completion of the remaining east berth portion of the State Pier in early Spring 2023,” Hammond said.
Despite the issues, Hammond said the target is still “substantial completion of the project” before Feb. 28, 2023, and final completion by June 2023.
Marlin Peterson, construction manager for the project from AECOM, said that dense material and large boulders were obstructing the pile driving. In July and August, two additional drill rigs and a driving pile were brought to the site to improve productivity and meet the scheduled completion date, Peterson said.
“What we hope to do over the next several weeks, is get existing pile driving data so that we can inform you at the next meeting with a revised completion date, not only for the balance of the areas that are moving well, but also for the State Pier complex,” Peterson said.
Already delayed by a lengthy permitting and appeals process, the cost of the project has ballooned to an estimated $250 million in an attempt to keep the deadline for South Fork. $255.5 million is currently available for the project, a figure that includes a contingency.
Asked what it would cost to resolve these construction issues, Peterson said he is working with the contractor to figure that out with the additional equipment on site, and that one possible solution is extending additional work days.
“Once we can confirm that the productivity numbers can be achieved, we can work through the cost of that and come back to the board for your review and approval,” Peterson said.
Dozens of Willington residents slam proposal for ‘gargantuan Godzilla’ warehouse off I-84
As about 350 people listened online and in person, a long procession of Willington residents on Tuesday night told town officials that the proposed TradeCenter 84 project is far too big and completely unwelcome.
“I love my little one-horse town. I don’t want it to change,” Hancock Road homeowner David Gemme told the planning and zoning commission. “I did not move into this town to be the truck haven of New England.”
“We can’t let this go to the next stage,” Benson Chan of Laurel Drive said. “We have to say no now. I haven’t met anybody who wants this.”
None of the roughly 30 speakers supported Hillwood Development Co.’s proposal to build a 1.5-million-square-foot warehouse just off Exit 70 of I-84.
After three hours of hearing from opponents, the commission continued its public hearing until Sept. 6 because it still had a list of more people waiting to speak.
The audience at the Hall Memorial School gym was standing-room only, with the bleachers crowded with residents. More than 100 other people followed the discussion online.
One after another, residents told the commission that a six-story mega-warehouse doesn’t belong in a sleep suburb of fewer than 6,000 people. One called it “a gargantuan Godzilla.”
Some cited financial reasons and others emphasized the character of the town or environmental concerns; regardless, the crowd applauded after each speaker.
“Property values can only be negatively impacted by a project of this magnitude. It’s going to be a drain on services, the quality of life is going to be diminished,” Donald Parizek of Trask Road said.
Parizek cited Secaucus and other heavily industrialized sections of northern New Jersey as a warning, saying “It’s not a pleasant site. The traffic, the noise, the trash — it all adds up.”
The TradeCenter84 plan has led opponents to start an online petition calling for commissioners to reject the developer’s bid for a zone change. As of Wednesday, the petition — tinyurl.com/ycxxuacc — had gotten 1,170 signatures.
Texas-based Hillwood is eyeing 160 acres of woodlands just behind River Road for a massive warehouse with more than 220 loading bays along with parking spaces for 700 tractor trailers and 500 workers.
The company said it would bring hundreds of jobs and a net gain of about $2.7 million a year in tax revenue for the town. Additionally, the operation would spur more economic development in that section of town, according to Hillwood’s representatives.
But opponents argued those reasons aren’t good enough.
“The tax argument is bogus. This would lower property values in Willington and surrounding towns,” said Penny Dionne of Fisher Hill Road. “This proposal is a threat to everything Willington represents. Protect our Willington: Once it’s destroyed it will be gone forever.”
Ed Taiman of Lisa Lane drew some of the loudest applause of the evening when he said he would rather face higher taxes than see such a massive operation start in town.
“Yes a couple of million dollars a year is nice. We’d all like to see that. But I’d rather pay it than have this project,” Taiman said. “History has shown that when you increase tax revenue they find a way to spend it.”
Taiman also said the parks and recreation commission is against the project because it has worked for years to build the town’s recreational center nearby on River Road.
“We stand united in our opposition,” he said. “We urge you not to approve this facility.”
Kathy Demers said the conservation commission is concerned about water runoff, soil erosion and new demand for water by the warehouse.
“We strongly recommend the applicant consider scaling back the height and size of the building and parking areas.”
NEW HAVEN — In an at-times tumultuous meeting, the Tweed New Haven Airport Authority approved a new 43-year lease and management agreement with a subsidiary of its longtime contract operator, Goldman Sachs-owned Avports LLC, on Wednesday, opening the door for a $100 million airport expansion.
The meeting took place with East Haven Mayor Joe Carfora speaking forcefully against the lease and expansion and all four East Haven-appointed members voting no. A number of airport neighbors and other residents showed up at the airport despite the fact that the meeting was held virtually via Zoom and also spoke against expansion after being admitted into the Zoom meeting.
The vote came after the East Haven appointees failed in an attempt to table the lease — and most other actions at the meeting — on the basis that airport officials didn’t give them enough time to review 660 pages of material sent to them Sunday.
“When the Authority and Avports first announced this historic partnership last year, we had one goal: give the people of southern Connecticut the airport they want and deserve,” said Tweed Authority Executive Director Sean Scanlon in a release issued immediately after the vote. “Today’s vote is yet another positive step in that direction.
“An improved Tweed will provide the air service that southern Connecticut has asked for, and it will spur continued economic development and job growth along the way,” said Scanlon, who is expected to leave his position if he is elected state treasurer in November. “We have more steps ahead and will continue working with all our local partners as this successful project proceeds.”
“While you would say that this has been rushed, I would say that what we’re talking about today is the same thing we stood up and talked about in May of 2021,” Scanlon said at the meeting, addressing concerns raised by both airport neighbors and East Haven members of the authority board.
“Nothing in this is definite,” he said, pointing out that “we’re still doing an environmental assessment ... If anything is found not to be environmentally sound, it won’t happen,” Scanlon said. “ Tonight is just moving the process forward. It is not the final vote on the project.”
Authority Chairman John Picard, former mayor of West Haven, said at the end of meeting, “We volunteer and we really do what we feel is best ... for the region and for all of us, and we’re going to continue to do what we feel is best.”
Picard, who at the end of the meeting was unanimously reelected as chairman, said in the release, “Our focus in expanding the airport is to offer people more choices and more destinations, while remaining convenient and an economic driver for our local communities. We’ve been grateful for our long-term partnership with Avports and will continue to provide top-notch air travel experiences and services for our community.”
Avports CEO Jorge Roberts said, “We are excited to enter into this new agreement with Tweed and our partners in local government. This lease agreement provides a first-of-its-kind flexibility to airport municipalities. We recognize our responsibility to ensure a sustainable airport and to expand upon Avports’ track record as a leader in environmental, social, and governance principles. The future is very bright at HVN.”
The authority, through the long-term sublease and development agreement, will cede control of certain portions of the airport to The New HVN LLC, a new corporation that is a subsidiary of Avports LLC.
Avports, owned by a subsidiary of Goldman Sachs, has managed Tweed for the past 23 years. As part of the agreement, it will invest money in airport operation and expansion, eliminating $1.8 million in annual city and state subsidies.
The plans calls for a broader partnership under which Avports will invest about $100 million to extend the usable length of Tweed’s runway from 5,600 feet to 6,635 feet by paving currently grassy runway safety area.
They also call for Avports to build a new 74,000-square-foot, carbon-neutral terminal with four to six departure gates on the East Haven side of the airport, with a new entrance to be constructed off Proto Drive in East Haven.
Avports also would be fully responsible for Tweed’s operating expenses, eliminating the need for subsidies.
The lease and development agreement lays out what The New HVN LLC would spend on community benefits, including $1.5 million on traffic management — split between New Haven and East Haven — $1.5 million on noise mitigation, expanding it to include full blocks when part of a block qualifies, $1.75 million as an “unassigned” community benefit for smaller issues in either New Haven or East Haven, and $250,000 for general aviation noise abatement.
The reactions of the New Haven and East Haven mayors could not have been more different.
“Today’s announcement is one more important step forward toward ensuring long-term stability at Tweed Airport that will grow our local economy, provide high-quality travel options for residents, good-paying jobs for families and address critical noise, traffic, safety and financial concerns as well,” said New Haven Mayor Justin Elicker.
“I am thankful for the partnership and commitments made by the Tweed Board of Directors and Avports, and today’s lease approval is a meaningful milestone toward responsible growth and a long-term partnership at Tweed-New Haven Airport,” Elicker said.
Carfora told the authority, “I want it to be clear to my constituents: I am against the expansion of this airport to the East Haven side. I have asked consistently for a shared burden — and our requests have been uniformly denied. This agreement is being rushed, meetings and engagement were limited leading up to this vote using COVID-19 and remote meetings in order to limit transparency.
“The facts about how it is before you today are astounding,” Carfora said. “We were denied access to it last week by Mr. Scanlon. It was relayed to us Sunday, not enough time for any of our board members to fully digest and seek interpretation on what is contained in this document or its impact on the town. Having said that, it does not take an expert to see that there is not shared burden.
“East Haven takes it on the chin while we will inherit all the traffic, transient population, parking headaches, ecological strip-mining, noise, pollution and burden on our already taxed public safety departments that will come with this project, while at the same time giving New Haven most of the economic benefit, serving at the behest of Yale and Goldman Sachs,” Carfora said.
“I have said all along that I wanted to be a good neighbor,” he said. “It is simply not possible given the way this lease is being handled. Our town has signed nothing. We have agreed to nothing. We have hired specialized counsel, and federal aviation counsel. All avenues will be taken to protect our community.
“East Haven is not afraid of a street fight; we never have been,” Carfora said, “but it is clear that Mr. Picard, Mr. Scanlon, Mayor Elicker have partnered with Yale, AvPorts, and Goldman Sachs to create a plan that not only hurts the quality of life in East Haven, but also the quality of life for an entire section of the city of New Haven.”
He also revealed that “prior to this meeting, the Town of East Haven sent Mr. Scanlon, Mr. Picard” and other officials “a litigation hold letter to preserve any and all communications regarding this matter, and most importantly everything leading up to it.”
In addition to the lease and development agreement, the authority passed resolutions to approve an amended and restated lease between the city and the authority, accept a federal Small Community Air Service Development Program grant, create a new Advisory Committee made up largely of former board members, amend the authority’s bylaws, approve an amendment to the agreement with Avports and publish rules, regulations and minimum standards for the airport.
East Haven authority members Ken Dagliere, Linda Hennessey, Town Council member Ray Pompano and Kevin Coyle, led by Dagliere, tried unsuccessfully to table all of those resolutions, saying in each case they did not have enough time to read and digest them. Each vote failed and each subsequent motion to approve a resolution passed by a 9-4 vote.
The authority also unanimously elected Guilford First Selectman Matt Hoey to serve as vice chairman, former New Haven city official Serena Neal-Sanjurjo to serve as treasurer and East Haven appointee and former Town Council member Hennessey to serve as secretary.
About 20 members of the public spoke prior to the votes, with all but about four of them speaking against expansion and/or what they felt was the authority “rushing” to approve the lease and development agreement.
“I’m appalled that some of these members are on here today,” said East Haven resident and frequent Tweed critic Lorena Venegas, referring to several board members whose terms have expired but have yet to be replaced. She said the agreement and expansion are premature because “you cannot doing anything with ... Avports without having an entrance and egress from East Haven.”
“I am just appalled at the behavior of the board, Tweed and the town of New Haven, the way they treat the residents,” said East Haven resident Jean Edwards-Chieppo. “It’s as if they do not matter, they do not exist.”
“It is appalling! Find your conscience. It’s absolutely diabolical,” Chieppo said. “This is not a joke. It’s our lives.”
Garrett Sheehan, president of the Greater New Haven Chamber of Commerce, spoke in favor of the lease agreement, saying it would continue the controlled growth” taking place at Tweed.
Barbara Malmberg of East Haven, a project manager for REX Development in New Haven, said she bought her home near the airport because she wanted easy access to flights. “REX Development supports the responsible growth of the region” and “this is an opportunity to make that happen, big-time,” she said.
Lisa Bassani, of New Haven’s Morris Cove section, said of Tweed neighbors, “We feel disregarded. We feel unheard ... We live here. We live in the community. It’s a residential neighborhood. We have a K-8 school here. We have a church here ... We have not been heard.”
City to match funds for Naugatuck River Greenway Trail
PAUL HUGHES
Waterbury Mayor Neil M. O’Leary says the city is moving quickly to authorize $5 million in local matching funds required under a recently approved $23.1 federal infrastructure grant.
O’Leary said the funding request will be on the Board of Aldermen’s agenda for its Sept. 8 meeting during a remote news conference with U.S. Rep. Jahana Hayes, D-5th District, and U.S. Transportation Secretary Pete Buttigieg.
The $28.1 million in federal and local funding will be used to continue construction of the Naugatuck River Greenway Trail, create a riverfront park on Jackson Street, make improvements to West Main Street and build charging stations for electric vehicles at the city train station.
Buttigieg said Waterbury faced some stiff competition because the U.S. Department of Transportation received nearly 1,000 funding requests for this round of $2.2 billion in federal funding for local transportation projects.
“We got about $13 billion worth of applications for just over $2 billion in funding,” he said.
Buttigieg said the $23.1 million request from Waterbury was among the 166 applications for Rebuilding American Infrastructure with Sustainability and Equity grants that were approved.
The Transportation Department also approved funding for a second project in the 5th Congressional District. The Capitol Region Council of Governments was awarded a $16.3 million grant to help close the last gap in the 84-mile Farmington Canal Heritage Trail from New Haven to Northampton, Mass. This $30 million project also will connect the multiuse trail to the CTfastrak trail in New Britain.
“This investment is unprecedented and really amazing,” Hayes said, noting she lobbied U.S. transportation officials in April to back the two projects.
Only one other Connecticut project received a RAISE grant. Stamford was awarded $2.1 million for planning traffic and pedestrian safety improvements along a 1.1-mile stretch of West Main Street.
“These are really some of the very strongest applications that came in,” Buttigieg said.
Waterbury will use some of its $23.1 million federal grant to construct the next 2.3 miles of the Naugatuck River Greenway Trail. O’Leary told Buttigieg construction of the first phase of the trail from the Naugatuck border to Eagle and South Main streets is expected to be completed next month.
“It is amazing how that has connected this community in so many different ways,” the mayor said, “and, by the way, before it was even near finished it was impossible to keep people away from there. They were so excited.”
O’Leary said the first section has linked the challenged South End neighborhood with downtown Waterbury.
“This has just been amazing,” he said. “To be able to secure this RAISE grant will just keep the momentum going on a project that we have been working on for the past 10 years.”